On 10/28/2014 04:20 AM, Matt Kassawara wrote:
> If other reasons (outside of the installation guide) exist to move it on
> the 29th rather than wait until after the summit, I can deal... but
> backporting patches for RHEL/CentOS/Fedora will take more time and
> effort. Not our fault RDO can't push release packages out in a
> reasonable amount of time.
You ask for a day - and I had one day buffer when I asked for the 29th ;)
So, let's wait a day if that works for Anne. Anne, if you want me to
work with infra to cut the branches, I can do that as well.
Otherwise after the 7th of November would work as well,
Andreas
--
Andreas Jaeger aj@{suse.com,opensuse.org} Twitter: jaegerandi
SUSE LINUX Products GmbH, Maxfeldstr. 5, 90409 Nürnberg, Germany
GF: Jeff Hawn,Jennifer Guild,Felix Imendörffer,HRB16746 (AG Nürnberg)
GPG fingerprint = 93A3 365E CE47 B889 DF7F FED1 389A 563C C272 A126
More information about the OpenStack-docs
mailing list