[openstack-dev] [release] Release countdown for week R-21, September 29 - October 6
Sean McGinnis
sean.mcginnis at gmx.com
Thu Sep 28 18:46:09 UTC 2017
Welcome to our regular release countdown email.
Development Focus
-----------------
Team focus should be on spec approval and implementation for priority features.
General Information
-------------------
Just one more mention - teams should review their release liaison information
and make sure it is up to date [1]. We would love to have all the liaisons
attend the release team meeting every Friday [2].
[1] https://wiki.openstack.org/wiki/CrossProjectLiaisons
[2] http://eavesdrop.openstack.org/#Release_Team_Meeting
We are already two weeks out from the Q-1 milestone. Please be aware of project
specific deadlines leading up to this milestone.
As mentioned, Newton EOL is coming up the week before Q-1. To wrap things up
for that, any final Newton library releases should be done this week to give a
small window before any final Newton service releases.
Upcoming Deadlines & Dates
--------------------------
Queens-1 milestone: October 19 (R-19 week)
Forum at OpenStack Summit in Sydney: November 6-8
Last Newton Library releases September 25-29 (R-22)
Newton Branch EOL October 11th (R-20 week)
--
Sean McGinnis (smcginnis)