[openstack-dev] [release] Release countdown for week R-11, December 9-15

Sean McGinnis sean.mcginnis at gmx.com
Thu Dec 7 20:18:46 UTC 2017


Short and sweet this week.

Development Focus
-----------------

Queens-2 is here, but if you were late requesting the release, please do so as
soon as possible.

General Information
-------------------

Teams should be focused on implementing planned work for the cycle. It is also
a good time to review those plans and reprioritize anything if needed based on
the what progress has been made and what looks realistic to complete in the
next few weeks.

Upcoming Deadlines & Dates
--------------------------

Final non-client library release deadline: January 18
Final client library release deadline: January 25
Queens-3 Milestone: January 25
Rocky PTG in Dublin: Week of February 26, 2018

-- 
Sean McGinnis (smcginnis)