On 08/03/2017 04:50 PM, Doug Hellmann wrote:
> Excerpts from Dmitry Tantsur's message of 2017-08-03 16:16:12 +0200:
>> Hi!
>>
>> On 08/03/2017 03:03 PM, Thierry Carrez wrote:
>>> Welcome to our regular release countdown email!
>>>
>> <snip>
>>>
>>>
>>> Actions
>>> -------
>>>
>>> Deliverables following the cycle-with-milestones model should post a RC1
>>> openstack/releases request during the week (X.0.0.0rc1), together with a
>>> stable/pike branch request. It should include something like this:
>>>
>>> ...
>>>     - projects:
>>>         - hash: YOURHASH
>>>           repo: openstack/YOURPROJECT
>>>       version: YOURVERSION.0.0.0rc1
>>> branches:
>>>     - location: YOURVERSION.0.0.0rc1
>>>       name: stable/pike
>>>
>>> Deliverables following the cycle-with-intermediary model should also
>>> create their Pike release branch next week. That means potentially
>>> making a last Pike release, and in all cases posting the stable/pike
>>> branch creation request:
>>>
>>> ...
>>> branches:
>>>     - location: YOUR.PIKE.VERSION
>>>       name: stable/pike
>>
>> https://releases.openstack.org/pike/schedule.html mentions the week after next
>> (starting Aug 21) to be the last week for cycle-with-intermediary releases. Are
>> we expected to branch before that? Could you please clarify the hard deadline?
> 
> Stable branches are always created from tagged releases. So, you
> need to prepare a release to serve as the base of the branch.
> 
> Milestone-based projects use an 0rc1 tag for that release, indicating
> that it is a release candidate. Those are scheduled for 10 Aug this
> cycle.
> 
> cycle-with-intermediary projects like Monasca should use a full
> regular release as the base of the branch. Those should be created
> some time between the RC1 week and that final deadline on 24 Aug.
> By selecting the cycle-with-intermediary model, you've indicated
> that you want more control over the release process and understand
> the risks, so you'll have to decide how to balance the timing of
> the branch on your own. Branching too early means you may have to
> backport more fixes and may have to make more patch releases.
> Branching later means your users have less time to test the released
> version that will ship as part of Pike.

Ok, this matches my current expectations.

> 
> After 24 Aug, we freeze the release repo for a week to give folks
> time to test the last release candidates for milestone-based projects.
> Only really critical fixes (installation deletes the entire database,
> or infects servers, or whatever) for any project will be released
> between 24 Aug and 30 Aug. Normal patch releasing usually resumes the
> following week, after we open the requirements repository again.
> 
> Releases from master after 24 Aug will be considered part of Queens, not
> Pike.
> 
> Does that help?

Yes, thanks!

> 
> Doug
> 
>>
>>>
>>>
>>> Upcoming Deadlines & Dates
>>> --------------------------
>>>
>>> RC1 target deadline (and HardStringFreeze): August 10
>>> Final Pike release: August 30
>>> Queens PTG in Denver: Sept 11-15
>>>
>>> As usual come find us on #openstack-release IRC channel if you have any
>>> questions or concerns.
>>>
>>
> 
> __________________________________________________________________________
> OpenStack Development Mailing List (not for usage questions)
> Unsubscribe: OpenStack-dev-request at lists.openstack.org?subject:unsubscribe
> http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev
> 




More information about the OpenStack-dev mailing list