[openstack-dev] [magnum] Schedule for rest of Kilo

Adrian Otto adrian.otto at rackspace.com
Fri Jan 23 21:46:12 UTC 2015


Steven,

Thanks for this email to capture and relay this decision from our IRC team meeting this week! I thought it might be helpful if I made a team calendar with an iCal feed that our team can subscribe to that would include our team meeting schedule, and our milestones to help make our plans more visible to the team. I can set this up if there is interest. Thoughts on this?

Cheers,

Adrian

On Jan 21, 2015, at 8:42 AM, Steven Dake <sdake at redhat.com> wrote:

> TLDR; moving Magnum to match upstream release scheduling intersecting k3
> 
> As discussed in our last IRC meeting we want to merge our Magnum milestone schedules with the upstream OpenStack schedules as soon as feasible.  We think it is feasible to merge release schedules for K3.  As such, We have picked the following dates for our schedules:
> 
> Milestone #2:February 16th
> Milestone #3 - merging with all OpenStack K3: March 19th
> magnum rcs April 9th-23rd
> magnum-2015.1 release - April 30th
> 
> From k3 forward, we will follow the Kilo release schedule here:
> 
> https://wiki.openstack.org/wiki/Kilo_Release_Schedule
> 
> __________________________________________________________________________
> OpenStack Development Mailing List (not for usage questions)
> Unsubscribe: OpenStack-dev-request at lists.openstack.org?subject:unsubscribe
> http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev




More information about the OpenStack-dev mailing list