[openstack-dev] [release] preparing your mitaka-1 milestone tag

Robert Collins robertc at robertcollins.net
Thu Dec 3 20:13:26 UTC 2015


On 28 November 2015 at 03:32, Doug Hellmann <doug at doughellmann.com> wrote:
> Next week (Dec 1-3) is the Mitaka 1 milestone deadline. Release
> liaisons for all managed projects using the cycle-with-milestones
> release model will need to propose tags for their repositories by
> Thursday. Tag requests submitted after Dec 3 will be rejected.
...
> 3. Prepare a patch to the project repository removing the version
>    line from setup.cfg.
>
>    Set the patch to depend on the release patch from step 1, and
>    use the topic "remove-version-from-setup".

There is a gotchya here that may confuse people. The patch in step 3,
if prepared concurrently with the tag, will show versions regressing,
but in the gate it will do the right thing!

The issue is merely that if the local git revision doesn't reach the
tag, then as far pbr is concerned (and git describe), the new tag
doesn't exist, and so its like step 2 was skipped. So - to avoid
confusing anyone, make sure you base the patch for step 3 on top of
the revision being tagged in step 2.



-- 
Robert Collins <rbtcollins at hpe.com>
Distinguished Technologist
HP Converged Cloud