[openstack-dev] [RFC] Kilo release cycle schedule proposal

Sergey Lukjanov slukjanov at mirantis.com
Mon Sep 29 21:29:12 UTC 2014


+1

On Thu, Sep 25, 2014 at 7:02 AM, Morgan Fainberg
<morgan.fainberg at gmail.com> wrote:
>
>
> On Thursday, September 25, 2014, Thierry Carrez <thierry at openstack.org>
> wrote:
>>
>> Thierry Carrez wrote:
>> > Kilo Design Summit: Nov 4-7
>> > Kilo-1 milestone: Dec 11
>> > Kilo-2 milestone: Jan 29
>> > Kilo-3 milestone, feature freeze: March 12
>> > 2015.1 ("Kilo") release: Apr 23
>> > L Design Summit: May 18-22
>>
>> Following feedback on the mailing-list and at the cross-project meeting,
>> there is growing consensus that shifting one week to the right would be
>> better. It makes for a short L cycle, but avoids losing 3 weeks between
>> Kilo release and L design summit. That gives:
>>
>> Kilo Design Summit: Nov 4-7
>> Kilo-1 milestone: Dec 18
>> Kilo-2 milestone: Feb 5
>> Kilo-3 milestone, feature freeze: Mar 19
>> 2015.1 ("Kilo") release: Apr 30
>> L Design Summit: May 18-22
>>
>> If you prefer a picture, see attached PDF.
>>
>> --
>> Thierry Carrez (ttx)
>
>
> +1
>
> _______________________________________________
> OpenStack-dev mailing list
> OpenStack-dev at lists.openstack.org
> http://lists.openstack.org/cgi-bin/mailman/listinfo/openstack-dev
>



-- 
Sincerely yours,
Sergey Lukjanov
Sahara Technical Lead
(OpenStack Data Processing)
Principal Software Engineer
Mirantis Inc.



More information about the OpenStack-dev mailing list