Hi, We are getting close to the Xena release. So I created a tracking etherpad[1] with the schedule and TODOs. One thing that I want to highlight is that we will hit Feature Freeze on 3rd of September. As the timeframe between FF and RC1 is short I'm not plannig with FFEs. Patches that are approved before 3rd of Sept EOB can be rechecked or rebased if needed and then re-approved. If you have a patch that is really close but not approved before the deadline, and you think there are two cores that willing to review it before RC1, then please send a mail to the ML with [nova][FFE] subject prefix not later than 7th of Sept EOB. Cheers, gibi [1] https://etherpad.opendev.org/p/nova-xena-rc-potential
Hi, On Thu, Aug 19, 2021 at 11:27, Balazs Gibizer <balazs.gibizer@est.tech> wrote:
Hi,
We are getting close to the Xena release. So I created a tracking etherpad[1] with the schedule and TODOs.
One thing that I want to highlight is that we will hit Feature Freeze on 3rd of September. As the timeframe between FF and RC1 is short I'm not plannig with FFEs. Patches that are approved before 3rd of Sept EOB can be rechecked or rebased if needed and then re-approved. If you have a patch that is really close but not approved before the deadline, and you think there are two cores that willing to review it before RC1, then please send a mail to the ML with [nova][FFE] subject prefix not later than 7th of Sept EOB.
As of last Friday we hit Feature Freeze. So still open features needs to be re-proposed to Yoga. The nova-spec repo and launchpad can be used to propose thing to yoga already. If you have a feature that is really close to land the please follow the above FFE process. If you have a feature patch that was approved before the freeze but not landed yet then those patches can be rechecked or rebased and re-approved if needed. Please let the core team know. Cheers, gibi
Cheers, gibi
participants (1)
-
Balazs Gibizer