Greetings,


The TripleO CI team has just completed Sprint 40 / Unified Sprint 19 (Nov 21 thru Dec 18).  The following is a summary of completed work during this sprint cycle:


Next sprint starts Jan 3rd. The planned work for the next sprint [1] are still going to be defined, and may include component pipeline work and build out CentOS8 promotion and check jobs upstream.


The Ruck and Rover for this sprint are TBD. Please direct questions or queries to them regarding CI status or issues in #tripleo, ideally to whomever has the ‘|ruck’ suffix on their nick. Ruck/rover notes to be tracked in etherpad [2].


Thanks,


rfolco


[1] https://tree.taiga.io/project/tripleo-ci-board/taskboard/unified-sprint-20

[2] https://etherpad.openstack.org/p/ruckroversprint20