Hi, This is a reminder: end of next week is the planned deadline for the transition. (I've updated the lists of open & unreleased changes per project where there were any changes. See [2]) Thanks, Előd On 2021. 10. 11. 18:26, Előd Illés wrote:
Hi,
As Xena was released last week and we are in a less busy period, now it is a good time to call your attention to the following:
In a month Ussuri is planned to transition to Extended Maintenance phase [1] (planned date: 2021-11-12).
I have generated the list of the current *open* and *unreleased* changes in stable/ussuri for the follows-policy tagged repositories [2] (where there are such patches). These lists could help the teams who are planning to do a *final* release on Ussuri before moving stable/ussuri branches to Extended Maintenance. Feel free to edit and extend these lists to track your progress!
* At the transition date the Release Team will tag the *latest* Ussuri releases of repositories with *ussuri-em* tag. * After the transition stable/ussuri will be still open for bug fixes, but there won't be official releases anymore.
*NOTE*: teams, please focus on wrapping up your libraries first if there is any concern about the changes, in order to avoid broken (final!) releases!
Thanks,
Előd
[1] https://releases.openstack.org/ [2] https://etherpad.opendev.org/p/ussuri-final-release-before-em