[release] Release countdown for week R-16, Jun 22 - Jun 26

Sean McGinnis sean.mcginnis at gmx.com
Fri Jun 19 13:24:07 UTC 2020


Development Focus
-----------------

We are now past the victoria-1 milestone. Teams should now be focused on
feature development and completion of release cycle goals [0].

[0] https://governance.openstack.org/tc/goals/selected/victoria/index.html

General Information
-------------------

Our next milestone in this development cycle will be victoria-2, on
July 30. This milestone is when we freeze the list of deliverables
that will be included in the Victoria final release, so if you plan to
introduce new deliverables in this release, please propose a change to
add an empty deliverable file in the deliverables/victoria directory of
the openstack/releases repository.

Now is also generally a good time to look at bugfixes that were
introduced in the master branch that might make sense to be backported
and released in a stable release.

If you have any question around the OpenStack release process, feel free
to ask on this mailing-list or on the #openstack-release channel on IRC.

Upcoming Deadlines & Dates
--------------------------

Victoria-2 milestone: July 30
Ussuri cycle-trailing deadline: August 13